Uttar Pradesh Metro Rail Corporation (UPMRCL) has announced that Larsen & Toubro (L&T) was the lowest bidder for the civil construction of Package AGCC-07, the Agra Metro Line-2. A 14.2-station elevated viaduct, a 530-meter bridge to Kalindi.
Vihar Depot, and a 2.61-kilometer viaduct extension from Sadar Bazar Metro station to Line-1’s PAC Depot are all part of the ₹1,466.49 crore contract. Additionally, this contract includes work from the AGCC-06 package that was discarded. Larsen & Toubro.
(L&T) has been awarded a significant contract valued at ₹1,466.49 crore by the Uttar Pradesh Metro Rail Corporation (UPMRC) for the construction of Agra Metro’s Line-2, under Package AGCC-07. This development is a pivotal component of the Agra Metro Phase 1 project, aiming to enhance urban mobility in the historic city.
Scope of the Project
The contract encompasses the design and construction of a 15.09 km elevated viaduct stretching from Agra Cantt. Metro Station to Kalindi Vihar Metro Station. This includes the development of 14 elevated stations at key locations:
- Agra Cantt
- Sadar Bazar
- Pratap Pura
- Collectorate
- Agra College
- Hariparvat Chauraha
- Sanjay Place
- M.G. Road
- St. John’s College
- Sultanganj Crossing
- Kamla Nagar
- Foundry Nagar
- Agra Mandi
- Kalindi Vihar
Additionally, the project includes a 530-meter viaduct leading to the Kalindi Vihar Depot and a 2.61 km viaduct extension from the north of Sadar Bazar Metro Station to Line-1’s PAC Depot. This extension was previously part of the AGCC-06 package, which was canceled and subsequently integrated into the current contract.
Bidding Process and Financials
The tender for Package AGCC-07 was floated by UPMRC in December 2023, with an estimated cost of ₹1,529.29 crore and a completion timeline of 24 months. The bidding process saw participation from six firms, with L&T emerging as the lowest bidder at ₹1,466.49 crore, which is ₹62.79 crore (4.11%) below UPMRC’s estimate.
Strategic Importance
This contract signifies L&T’s re-engagement in elevated metro projects in northern India, as their recent projects have predominantly focused on underground tunneling works in cities like Delhi and Patna. The Agra Metro Line-2 project is poised to enhance urban connectivity, reduce traffic congestion, and provide a modern transit solution for residents and visitors. The integration of advanced infrastructure is expected to stimulate economic growth and improve the quality of life in Agra.
Funding and Timeline
The project is financed by the European Investment Bank (EIB) through a €450 million loan, underscoring international collaboration in India’s urban development initiatives. Pre-construction activities are anticipated to commence in early October 2024, with full-scale construction expected by December 2024. The project aims for completion within a 24-month timeframe, targeting operational readiness by late 2026.
The awarding of the Agra Metro Line-2 construction contract to L&T marks a significant milestone in the city’s infrastructural development. This project is set to transform Agra’s public transportation landscape, offering efficient and sustainable mobility solutions that align with the city’s growth and modernization objectives.
Group Media Publication
Construction, Infrastructure and Mining
General News Platforms – IHTLive.com
Entertainment News Platforms – https://anyflix.in/
Legal and Law News Platforms – https://legalmatters.in/