For the Phase-IV portion of the metro project, the Delhi Metro Rail Corporation (DMRC) has issued e-tenders for the supply, manufacture, transportation, and erection of three unique steel spans at various locations. For the elevated integrated viaduct section of line-10 of the Aerocity-Tughlakabad corridor of phase-4, between Saket-G and Sangam Vihar, steel spans will be erected at Mandir Marg on the metro viaduct and two at Ambedkar Nagar T-Point on M.B. Road (one each at metro viaduct and PWD flyover level), requiring an investment of 25.23 crores and a completion period of 9 months.