According to Fortuna, the Séguéla Gold Project’s construction is 83 percent complete.

Nov. 2, 2022, VANCOUVER, British Columbia GLOBEE NEWSWIRE The Séguéla gold Project in Côte d’Ivoire is being built by Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI), and the company is happy to share an update on those efforts. The company decided to move on with building of a 3,750 tonne per day mill at Séguéla in September 2021, with the first gold pour anticipated in mid-2023 (refer to Fortuna news release dated September 29, 2021). In this news release, all references to money are stated in US dollars.

“We are glad to announce that the building development at Séguéla continues to track on-time and within budget despite a particularly difficult wet season,” said David Whittle, Chief Operating Officer for West Africa. “The operation is now moving,” Mr. Whittle continued.

With the creation of operational procedures and systems, the company may go ahead with the recruitment and onboarding of key senior staff, enabling a seamless transition from construction to operation.

Building Highlights

As of October 31, 2022, the project is 83 percent finished, and the first gold pour is still scheduled for the middle of 2023.
All SAG mill components have now been transported, and deliveries are still coming into Abidjan, Côte d’Ivoire; the final SAG mill package is scheduled to arrive in early December.
The structural, mechanical, and plumbing (SMP) contractor for the process plant has made progress on a number of work fronts.
The 90kV transmission line and substation are almost finished, and they are scheduled to be turned on in December.
The water storage dam now has 565,000 m3 of water in it.

(WSD), which meets the demands and requirements for commissioning and startup activities.
The tailings storage facility (TSFearthworks )’s and high density polyethylene (HDPE) lining will be finished by the end of 2022.
The mining contractor arrived at the location and started setting up.

Processing Facility

The critical path scopes for the plant have advanced quite well for Lycopodium. The primary construction projects as of the end of October include: Civil and concrete construction is nearly finished, and the SAG mill pedestals have been turned over to the SMP contractor.


Construction of the carbon-in-leach (CIL) tank and completion of the hydrostatic and settling
Completed are hydrostatic testing and water tank assembly.
The reagents storage facility, warehouse, and workshop have all been constructed.
In the crusher, surge bin, milling, and grinding regions, structural steel was built.
Installations of mechanical equipment for the thickening, intense leach reactor, and apron feeder started.
Conveyor installation is in progress.
Spools of steel pipe have started to be made.
The project’s critical path continues to include the delivery and installation of the SAG mill.

All components have been sent and are anticipated to be delivered to the site before the end of the year, despite risks and challenges associated with the global supply chain.
Bulk Earthwork at the Site

TSF and WSD construction is well underway. The WSD’s construction is almost finished, and as of the end of October, it has already collected about 565,000 m3 of raw water in preparation for commissioning and switching over to operations. Likewise, the TSF embankment, which is scheduled to be finished this quarter, has made significant progress.

HDPE lining has been installed on 48% of the TSF’s total surface area. The lining contractor is returning to the site to finish lining the TSF now that the wet season is over. The project’s recruitment efforts are well under way, and Mota-Engil, the mining services provider at Séguéla, has dispatched a team to the location. After being purchased, all long-lead equipment began to arrive in the nation in October.

operational adequacy

The mine’s operational phase is now being well-prepared for. Currently, Mota-Engil is working on civil projects related to the construction of its infrastructure, which includes offices, workshops, and an area for explosives magazines. It is anticipated that work on the ROM pad and preliminary grade control drilling will start.

The first shipment of mining machinery has arrived in Côte d’Ivoire, and other shipments of the mining fleet are anticipated during the quarter.

The general manager of operations and other senior management posts have been appointed, and operational mine team recruitment efforts are well underway. The remaining members of the operational team are still being recruited.

Commitments to projects as of October 31, 2022:
As the Séguéla gold Project’s development moves along, more information will be supplied about its construction. The photo collection for Séguéla’s construction may be found here.

Group Media Publication
Construction, Infrastructure and Mining   
General News Platforms – IHTLive.com
Entertainment News Platforms – https://anyflix.in/
Legal and Laws News Platforms – https://legalmatters.in/
Podcast Platforms – https://anyfm.in/

You May Also Like

Uncategorized

On the 111-km-long, still-under-construction Banihal-Katra Railway link, Northern Railway has made considerable progress by breaking through T-48 tunnel, the fourth-longest tunnel in Indian Railways,...

2025

In order to assure compliance with essential standards for horizontal and vertical clearances, which are vital for safe passage, any bridge building across a...

2025

Elgi Equipments has introduced its STABILISOR compressed air stabilization technology to address issues of unstable compressor performance, inefficiency, and excessive wear caused by frequent...

Project

According to state transport minister P Paiwang Konyak, the north border railway has prioritised building a direct rail link from Dimapur-Dhansiripar to Kohima-Sechu by...

Copyright © 2020 ZoxPress Theme. Theme by MVP Themes, powered by WordPress.

Exit mobile version